If you have a customer that has failed to pay his invoice, you may
need to move quickly to preserve your most important means of collecting
on that debt. In Maryland, contractors that have provided certain
types of services are often eligible to obtain a Mechanics' Lien on
the property where products or services were provided. If the debt
is not paid after a Mechanics' Lien is ordered by the Court, the property
may be sold to satisfy the customer's obligation to you.
The following are some frequently asked questions about Mechanics'
Liens:
What types of contractors can get a Mechanics'
Lien?
Just about any contractor is eligible to apply for a Mechanics' Lien
if he furnishes labor or materials in connection with the improvement
of a building or land. The Courts have interpreted the law broadly
to include just about any contractor or supplier, including architects,
engineers, general contractors, plumbers, HVAC suppliers, electricians,
paving companies, landscapers, materials suppliers and rental equipment
providers. Many other trades and suppliers are covered as well.
What's the minimum amount a customer must
owe before a Mechanics' Lien can be obtained?
There is no minimum amount a customer must owe, but a Mechanics'
Lien can only be obtained if the property is improved by at least
15% of its value. The 15% test takes into account all work
performed by all contractors. So if a vacant lot worth $100,000
is surveyed and permitted by an engineering firm for $2,000, and then
graded and filled by a contractor for $13,000, both the engineering
firm and the contractor could obtain a Mechanics' Lien, even though
they could not do so if only their own work had been performed.
Do I have to appear in Court to get the
Mechanics' Lien?
Not always. After the initial filing is made with the Circuit Court,
the Court schedules a hearing and the property owner has about 30
days to file an answer. If the owner doesn't file an answer, the Court
usually cancels the scheduled hearing and the Mechanics' Lien is granted.
If the owner files an answer disputing some of the facts claimed by
the contractor, a hearing is held about 45 days after the initial
date of the Court's order. At that hearing, the contractor is usually
asked to testify and present facts that support the lien. The owner
also has a chance to testify and present facts. Sometimes the Court
grants the lien right after that hearing. Sometimes a trial date may
be set to provide additional facts and information. Most Mechanics'
Liens do not end up in a full trial.
How long does it take to get a Mechanics'
Lien?
There is a delay between the time the contractor's initial filing
is made with the Court and the time the Court issues an order directing
the owner to show why the Mechanics' Lien should not be granted. This
delay is simply based on Court administration and processing. After
the Court issues its show cause order, the owner is usually given
30 days to answer. If no answer is filed, or if the answer is improperly
filed, the contractor may obtain the Mechanics' Lien immediately.
Otherwise, it could take another 15 days if the Lien is granted at
the hearing. Or even another 6 months or more if a trial date is set.
Many Mechanics' Liens are granted without a hearing in about 30 days.
Many more are granted after the hearing in about 45 days. But some
go to trial and could take up to 6 months or more. The important thing,
however, is to file for the Mechanics' Lien because that will prevent
the owner from selling the property to avoid the lien.
Can I get a Mechanics' Lien if I'm a subcontractor?
Subcontractors can obtain Mechanics' Liens as well, but they are
subject to more extensive requirements and must provide additional
notices to the owner. For example, subcontractors must notify the
owner within 120 days after completion of the work that they intend
to seek a Mechanic's Lien. The notice must meet certain requirements.
If the notice is not provided, or does not meet the requirements,
the subcontractor may not obtain a Mechanics' Lien. Subcontractors
may also be limited in the amount they can obtain from the owner if
the owner paid the general contractor.
How much time do I have to file for a Mechanics'
Lien after the work is performed?
Contractors must file for a Mechanics' Lien within 180 days after
the work is performed or they may not obtain one. Subcontractors must
also have provided the notice described above to the owner within
120 days after the work is performed. This rule is firm and Courts
have routinely dismissed late-filed applications for Mechanics' Liens.
Note that if the work provided is ongoing, and all the subject of
a single contract (such as supplying lumber over the duration of the
project), the date that is important is the last date on which
products or services were provided. The Court will not require contractors
to continually seek liens throughout the term of the agreement, even
if invoiced amounts are adding up and are unpaid. If there are several
contracts, the important dates will be those dates on which work was
completed or stopped under each contract.
What if the customer doesn't own the property
where the work is performed?
A Mechanics' Lien can only be obtained if there is a contract between
the property owner and the contractor. Note, however, that a person
that has a contract to purchase a piece of property is generally deemed
to be the owner of that property. So if a contractor performs work
for the contract purchaser of the property, the contractor can usually
obtain a Mechanics' Lien against the property.
Do I have to have a written contract in
order to get a Mechanics' Lien?
You do not need a written contract in order to get a Mechanics' Lien.
But you must be able to establish that an agreement existed between
you and the owner for the work performed. There are many ways to establish
the existence of an agreement that is not written, and one important
method is to show that the owner was aware of the work you provided,
benefitted from it, and did not stop you when he knew you thought
there was a contract.
If I performed several projects for a customer,
do I need a Mechanics' Lien for each one?
A lot depends on your contract with the customer/owner. If the contract,
which does not have to be in writing, says that you will provide various
types of work over an extended period, you do not need a separate
Mechanics' Lien for each type of work. But if the contract is for
a specific project, such as to furnish and install a boiler, and you
have another contract to furnish and install an air conditioning unit,
you would likely need to obtain a Mechanics' Lien for invoices unpaid
under each contract.
Do I have to have a Maryland Home Improvement
Commission (MHIC) license to get a Mechanics' Lien?
If a Maryland Home Improvement Commission (MHIC) license is required
for the type of work that you provide, you must have the MHIC license
in order to obtain a Mechanics' Lien. The same is true of licenses
that are required for plumbers, electricians, engineers and others.
Note, too, that a customer is often able to avoid paying a contractor
if work is performed without the proper license.
If the customer sells his property before
I apply for a Mechanics' Lien, can I go after the buyer?
If a customer sells his property to a buyer in good faith, a contractor
no longer has the right to obtain a Mechanics' Lien against the property
for work performed for the seller. If, however, the contractor had
filed to obtain the Mechanics' Lien, even the day before the closing
date of the sale, the buyer will take the property subject to the
contractor's right to obtain the Mechanics' Lien. That is one reason
why it is important to file for the Mechanics' Lien even if you think
you can negotiate with the customer to obtain payment.
If I get a Mechanics' Lien and other contractors
or mortgage holders do as well, who has priority if the property is
sold to satisfy the debts to us?
If there are multiple lien holders, the proceeds from the sale of
the property will be applied in the order in which the liens were
obtained. First come, first served. This rule often gives contractors
superior rights over even a bank that holds the mortgage on the property.
If I can't get a Mechanics' Lien, what else
can I do to collect what is owed to me?
If you can't get a Mechanics' Lien, you have other options to collect
the debt, including suing for breach of contract. If you win a lawsuit
for breach of contract, the judgment will also act as a lien on any
property the defendant has in the county in which the judgment is
obtained. You can also enter the judgment in other counties to obtain
a judgment lien on real estate in those counties as well.
If you have additional questions about Mechanics' Liens, or to discuss
the facts of your particular situation, please contact
the Maryland law offices of Thomas Lynch & Associates for a free
initial consultation and case evaluation.
Thomas Lynch & Associates
The Crosby Building
705 Melvin Avenue, Suite 104
Annapolis, MD 21401
Phone: (410) 349-4990
Fax: (443) 926-0574
e-mail
Thomas Lynch & Associates provides legal advice to
businesses throughout Maryland including Anne Arundel County, Howard
County, and Baltimore County, as well as the cities of Baltimore,
Arnold, Odenton, Crofton, Pasadena, Severna Park, Columbia, Ellicott
City, Elkridge, Glen Burnie, Riva, Edgewater, Annapolis, and Bowie.